Whangārei District Council

Getting a Relocated House Consented in Whangārei

WDC covers the greater Whangārei urban area and surrounding rural districts including Hikurangi, Ruakākā, Mangakahia, and the Bream Bay area. They use an online portal called Objective Build for all consent applications.

⚠️ Important: Do not move the house before your building consent is granted. Moving prior to consent is a breach of the Building Act and can result in costly enforcement action.

Quick Facts

⏱️
Processing Time
20 working days (statutory)
💻
How to Apply
Online via Objective Build portal
📞
Phone
09 430 4200
📍
Office
Forum North, Rust Ave, Whangārei
🌐
Website

The Step-by-Step Process

1
Do this first

Check your receiving site against the District Plan

Before anything else, confirm that your receiving site is zoned appropriately for a residential dwelling and that there are no overlays (flood hazard, coastal hazard, heritage) that will complicate things. You can check this on the WDC GIS mapping tool on their website or call them for a pre-application chat — this is free and can save significant delays later.

💡 Ask WDC specifically whether a resource consent is also required in addition to a building consent. Rural zones and some coastal areas often need both.
2
Commission this

Get a structural engineer's report on the house

WDC requires a report from a registered structural engineer (or Licensed Building Practitioner with the right scope) assessing the condition of the house prior to relocation. This report must confirm the building is structurally sound and suitable for relocation. Expect to pay $800–$2,500 depending on the size and age of the house.

💡 Older houses (pre-1970s) may require weathertightness assessment as well. Ask your engineer upfront.
3
Commission this

Get a foundation design from a registered engineer

Your receiving site will need a foundation design specific to the ground conditions. In many Northland soils this requires a geotechnical assessment first. The foundation design must comply with NZ Building Code clause B1 (Structure). Budget $1,500–$4,000 for foundation design, more if a geotech report is also needed.

💡 If the site has never had a dwelling on it, a geotech report is almost always required. Allow 2–4 weeks for this step.
4
Prepare & submit

Prepare your building consent application

Register for an account on WDC's Objective Build portal and submit your application online. You'll need to include: the completed application form, site plan, floor plans and elevations, structural engineer's report, foundation design, certificate of title, and any other documents relevant to your site. WDC will vett the application and issue an invoice for the lodgement fee before processing begins.

💡 WDC offer a pre-application meeting service. For a complex site, this is worth doing — it can identify missing documents before you lodge and avoid delays.
5
Wait period

Processing — 20 working days

WDC has 20 working days from receipt of a complete application to issue consent. If they need further information (RFI), the clock stops until you respond. WDC will communicate via Objective Build — check it regularly. Respond to any RFIs promptly and completely to avoid extended delays.

✗ The clock only starts once your application is deemed complete and fees paid. Incomplete applications can sit for weeks before this happens.
6
Get permits

Obtain NZTA transport permits

While your building consent is being processed, arrange your transport permits through NZTA (0800 699 000). You'll need an oversize permit for anything over 2.5m wide, and a special permit plus police escort for loads over 4.3m wide. Allow 10+ working days for standard permits.

7
Move day

Relocate the house — after consent is granted

Once building consent is in hand, the house can be moved. Your contractor handles the physical relocation. Notify power lines companies (Northpower for most of Northland) well in advance — they need to raise or disconnect lines along your route. This can take 2–4 weeks to arrange.

✗ Do not move the house before your consent is granted. This is a breach of the Building Act.
8
On site

Inspections during construction

WDC building inspectors must inspect work at key stages: foundation excavation, foundation pour, pre-line (before internal linings go on), and final. Book inspections through Objective Build. All inspections must pass before you proceed to the next stage.

9
Final step

Apply for Code Compliance Certificate (CCC)

Once all work is complete and all inspections passed, apply for your Code Compliance Certificate through Objective Build. WDC has 20 working days to issue the CCC. This is the document that confirms your house is legally established on its new site and is required for the house to be occupied and for future sale.

💡 Don't skip this step — without a CCC the house technically cannot be occupied and will cause problems when you try to sell.

Documents You'll Need

Completed building consent application (via Objective Build)
Certificate of Title for receiving site
Site plan (to scale, showing setbacks and boundaries)
Floor plans and elevations of the house
Structural engineer's report on existing building
Foundation design by registered engineer
Geotechnical report (if required by engineer)
Services connection plan (water, wastewater, power)
NZTA transport permit (arranged separately)
Interconnected smoke alarm specification (required from Nov 2024)

Common Mistakes to Avoid

Moving the house before consent is granted
Not checking if a resource consent is also required
Submitting incomplete plans — causes RFIs and delays the clock
Forgetting to notify Northpower about overhead line clearances
Starting foundation work before booking the excavation inspection
Not applying for the CCC once work is complete
Assuming your site doesn't need geotech — check with your engineer

Whangārei District Council — Building Team

For pre-application queries, call or visit the building team at Forum North. The Objective Build portal handles all online applications. For complex sites, a pre-application meeting is strongly recommended.

Far North District Council

Getting a Relocated House Consented in the Far North

FNDC covers Kaitāia, Kerikeri, Paihia, the Bay of Islands, and all rural areas north of Whangārei. The Far North has specific requirements around tiny homes and relocatable buildings, and actively enforces consent rules in this area.

⚠️ FNDC warning: There has been an increase in relocatable homes installed in the Far North without consent. FNDC actively enforces this. Any building with sanitary fittings (sink, toilet, shower) requires a building consent regardless of size.

Quick Facts

⏱️
Processing Time
20 working days (allow 6–8 weeks)
💻
How to Apply
Online via FNDC portal or in person
📞
Phone
0800 920 029
✉️
Email
BuildingCompliance@fndc.govt.nz
🌐
Website

The Step-by-Step Process

1
Do this first

Check if the house already has a consent or CCC from the manufacturer

If you're buying a relocatable home, ask the seller or manufacturer for the Exemption Number and Certificate, or Code Compliance Certificate (CCC), issued when the house was originally built. If the manufacturer obtained this properly, you may only need a wastewater and foundation consent for the receiving site — saving significant time and cost.

💡 Contact FNDC's building compliance team via their RFS (Request for Service) system to verify any documents provided by the seller — this advice is free.
2
Check your site

Confirm site zoning and any overlay requirements

The Far North has significant areas of coastal hazard zones, flood plains, and heritage overlays — particularly around the Bay of Islands, Hokianga, and low-lying rural areas. Check the FNDC District Plan or call a planner to confirm whether your receiving site has any additional requirements or needs a resource consent.

✗ Rural and coastal sites in the Far North frequently require resource consent in addition to building consent. Confirm this early.
3
Commission this

Structural assessment and foundation design

FNDC requires a structural engineer's assessment of the building and a foundation design for the receiving site. If the house doesn't have an existing CCC, a more thorough condition report will be needed. If your site has difficult ground conditions — expansive clay is common in many Far North areas — a geotechnical report will be required before foundation design can proceed.

4
Prepare & submit

Submit building consent application using Form 2

FNDC uses an updated Form 2 for all building consent applications — make sure you download the current version from their website. Submit your completed application with all supporting documents to BuildingCompliance@fndc.govt.nz or through their online portal. FNDC will issue an invoice for the lodgement fee; work doesn't begin until this is paid.

💡 FNDC's building compliance team offer free advice before you submit. For anything complex, use this — call 0800 920 029 and ask to speak to building compliance.
5
Wait period

Processing — 20 working days

FNDC has 20 working days to process from receipt of a complete application. The Far North is known for thoroughness — get your documents right first time to avoid Requests for Further Information (RFIs) which pause the clock. Check your email and the portal regularly for any requests.

6
Arrange transport

NZTA permits and utility notifications

Arrange your NZTA transport permits in parallel with the consent process. For Far North routes — particularly SH1 north of Whangārei — some bridges have significant weight restrictions. Your contractor should assess the route and obtain permits. Notify Top Energy (the Far North lines company) about any power line clearances needed along the route.

7
Move & build

Relocate and complete site works

With consent granted, the house can be moved. Foundation work, services connections (wastewater, water, power), and any required reinstatement work follows. All work requiring inspection must be inspected by FNDC building officers at the relevant stages — do not proceed past an inspection point without approval.

💡 Interconnected smoke alarms are required in all new buildings from November 2024 — include this in your plans and specifications.
8
Final step

Code Compliance Certificate

Once all work is complete and inspections passed, apply for your CCC. FNDC has 20 working days to issue. The CCC is essential — without it the house is not legally habitable and will cause issues for future sale or finance.

Documents You'll Need

Completed Form 2 (current version from FNDC website)
Certificate of Title for receiving site
Architectural drawings — site plan, floor plans, elevations
Structural engineer's report (PS3/PS4 as applicable)
Foundation design by registered engineer
Geotechnical report (if required)
Wastewater design and approval
Existing CCC or exemption certificate from manufacturer (if available)
Proof of ownership or consent from owner
Interconnected smoke alarm specification

Common Mistakes to Avoid

Assuming a tiny home or relocatable doesn't need consent — it does if it has any sanitary fittings
Taking a seller's word that consent isn't needed — verify with FNDC directly
Not checking for coastal or flood hazard overlays on your site
Using an outdated Form 2 — FNDC updated this form, always download fresh
Not notifying Top Energy about route power line clearances
Moving the house without consent

Far North District Council — Building Compliance

The FNDC building compliance team offer free advice before you apply. Contact them via their RFS (Request for Service) system on the FNDC website, by email, or by phone. For complex sites, this upfront advice can save weeks of delays.

Kaipara District Council

Getting a Relocated House Consented in Kaipara

KDC covers Dargaville, Mangawhai, Ruawai, Maungaturoto and surrounding rural areas. Kaipara has specific additional District Plan requirements for relocated (second-hand) dwellings — over and above the standard Building Act requirements.

⚠️ Kaipara-specific: All exterior reinstatement work on a relocated building must be completed within 12 months of delivery to site. This is a District Plan condition, not just a Building Act requirement — KDC monitors compliance separately.

Quick Facts

⏱️
Processing Time
20 working days (statutory)
💻
How to Apply
Online via Objective Build
📞
Phone
0800 727 059
✉️
Email
buildingsupport@kaipara.govt.nz
🌐
Website

The Step-by-Step Process

1
Strongly recommended

Apply for a Project Information Memorandum (PIM)

KDC strongly recommends applying for a PIM before lodging your building consent. A PIM sets out everything KDC knows that could affect your project: compliance with the District Plan, drainage positions, natural hazards, and whether a resource consent is also required. It can be applied for standalone or together with your building consent application. KDC has 20 working days to issue a PIM.

💡 A PIM isn't mandatory but is very worthwhile in Kaipara — the district has a mix of soil conditions, flood zones, and coastal hazard areas that can throw up surprises. The PIM can prevent costly redesigns later.
2
Check this

Confirm District Plan requirements for relocated dwellings

Kaipara has specific District Plan rules for second-hand relocated dwellings that sit alongside the Building Act requirements. KDC's Monitoring Team (separate from the Building Team) enforces these. Key requirement: all exterior reinstatement work must be completed within 12 months of the building arriving on site. When you apply for building consent, you'll sign a declaration confirming this.

✗ This 12-month exterior reinstatement rule is monitored by KDC. A compliance visit will be done and if the exterior isn't completed neatly, remedial work will be required.
3
Commission this

Structural assessment and geotechnical report

A structural engineer's assessment of the house is required. Kaipara soils vary significantly — from good coastal sands around Mangawhai to expansive clays inland and soft alluvial soils in low-lying areas around the Kaipara Harbour. A geotechnical report is very commonly required before foundation design can proceed. Build 3–5 weeks into your timeline for this.

4
Get temporary consent if needed

Note: Temporary foundations don't need consent — permanent ones do

Kaipara has a specific provision: you do not need a building consent to relocate a house onto temporary foundations. However, a formal building consent is required before the building is used as a dwelling on permanent foundations. The building must not be used for habitation until legally certified. This can be useful if you need time to prepare your full application.

💡 This does not mean you can skip the process — it just gives you flexibility on timing if you need to move the house before the full consent is ready.
5
Prepare & submit

Submit building consent via Objective Build

Apply online through Objective Build. KDC circulates your application to multiple departments: planning, structural/geotech engineering, building, stormwater, wastewater, and drainage. Each discipline assesses compliance separately. If any department has questions, they'll issue an RFI which pauses the 20-day clock — so get your documents right the first time.

💡 Contact KDC's building support team before lodging for complex sites: 0800 727 059. Getting upfront guidance is worth the call.
6
Wait period

Processing — 20 working days

KDC aims for 20 working days. Because your application goes through multiple departments, RFIs are common. Respond through Objective Build promptly — responses go directly back to the processor handling your application. Make sure all consented plans are printed and available on site for inspectors and contractors.

7
Move & build

Relocate, foundations, and site works

With consent granted, move the house and begin foundation and site works. Note that building consent is valid for 12 months — work must commence within this period or the consent lapses. If you need an extension, apply before the 12-month expiry date. All inspection stages must be booked and passed through Objective Build.

✗ The consent lapses if work doesn't commence within 12 months. Extensions must be applied for before expiry — you cannot apply after the lapse date.
8
District Plan obligation

Complete exterior reinstatement within 12 months of delivery

KDC's Monitoring Team will conduct a compliance visit to check that the exterior of the dwelling — paintwork, decking, baseboards, architraves, roofing — is complete and tidy within 12 months of the house arriving on site. This is a District Plan condition. Budget for this in your project timeline and costs.

9
Final step

Apply for Code Compliance Certificate

Once all work is complete, apply for your CCC through Objective Build. This is essential for the house to be legally occupied and for future sale. KDC has 20 working days to issue the CCC.

Documents You'll Need

Building consent application via Objective Build
Certificate of Title for receiving site
Site plan, floor plans, elevations (to scale)
Structural engineer's assessment of the building
Geotechnical report (very commonly required)
Foundation design by registered engineer
Wastewater and drainage design
'Confirmation from Dwelling Relocation Applicant' declaration (12-month reinstatement)
PIM (recommended — apply before or alongside consent)
Interconnected smoke alarm specification

Common Mistakes to Avoid

Not getting a PIM first — Kaipara has many sites with surprises
Underestimating the geotech requirement — very common in this district
Missing the 12-month exterior reinstatement deadline
Letting the building consent lapse by not commencing work within 12 months
Not checking Kaipara Harbour and coastal flood zones on your site
Occupying the house before the CCC is issued
Ignoring the District Plan requirements — the Monitoring Team checks these separately from building compliance

Kaipara District Council — Building Support

KDC's building support team can advise before you lodge. For complex sites, a pre-application meeting is recommended. All applications go through Objective Build — register online or contact the team for assistance if you can't access it.

Information is based on publicly available council guidance and is indicative only. Council requirements can change. Always verify current requirements directly with the relevant council before proceeding with any project. FillFinder is not a substitute for professional advice.